where will it be built..?
you'll also gonna need hardware to mount the 2x8 or 2x6 according to that towns code to the wall of the house. concrete because you have to dig 3 feet down (below freezing point)
boxes and boxes and more boxes of screws. pleanty of 4x4's
is it gonna be a single deck or a 2 teir deck.? how high off the ground or is it ground level..?
are you pulling a permit for it.?
if you serious want it done let me know. i'll do it for you.
|
I got the permit, it will be buyil in pa it wil lbe 3 level
level one ground level, level two about one foot above ground, lebel 3 will go up about 2 feet over level 2 and have a hot tup there..
totla Sq footage will be about 880
it will look like this
|== |_________
| |
|____________|
I have all the foundation thinsg dug and ppured and inspected already now i need to getteh rest of it built.. iwas going to do it my slef ut have no time